The Summary

  • A patio is only as stable as the subgrade beneath it; in Southwest Michigan, a standard 4-inch base is a guaranteed recipe for frost heave and settling.

  • We excavate 11–13 inches deep to install a hydrostatic barrier (geotextile fabric) and an 8-inch compacted aggregate base that bridges soft clay soils.

  • If you cannot drive a truck across the base material before the pavers are laid, the foundation is not ready.


The Anatomy of Movement (Why We Dig Deep)

Unilock Beacon Hill Alpine Grey paver patio

Homeowners often view a patio as a surface purchase—choosing colors, textures, and patterns. However, the psychological stress of a patio comes three years later, when you trip over a heaved paver while carrying a tray of drinks, or when you notice a puddle forming exactly where you want to place your chair. These aren't just cosmetic annoyances; they are structural failures that alter how you use your backyard. When a patio settles, you stop using the uneven edges. You subconsciously avoid the areas that hold water. The space shrinks.


In Arizona or Florida, a contractor might get away with scraping off the grass and throwing down some sand. In Michiana, that is negligence. Our soil is predominantly heavy clay, which holds water like a bowl. When that water freezes in January, it expands, pushing everything above it upward. When it thaws, the clay turns to soup, and the heavy pavers above it sink.


This is why we strictly enforce an 11 to 13-inch excavation depth. We aren't just making room for stone; we are removing the unstable organic soil and replacing it with a structural column that acts as a bridge over the volatile clay.


The Iceberg: What Happens Underground

Technical Anatomy of the Salzman Standard

The difference between a patio that lasts 25 years and one that fails in three is entirely invisible to the naked eye. It happens in the "Iceberg"—the deep engineering buried underground.


1. The Separation Layer (Geotextile Fabric)

When we excavate down to the raw subgrade, we almost always encounter sticky, dense clay. If we were to dump aggregate stone directly onto this clay, the traffic from above and the hydraulic pressure from below would eventually mix the two. The heavy stone would sink into the clay, and the clay would pump up into the stone. This creates a "mud pump" effect, destroying the structural integrity of the base.


We install a heavy-duty non-woven geotextile fabric immediately after excavation. This fabric has high tensile strength but remains permeable to water. It prevents lateral movement of the base and ensures the stone never mixes with the soil. It is the insurance policy for the entire project.


2. The 8-Inch Compacted Aggregate Base

8" patio base being installed

Standard "code" often suggests a 4-inch base. We reject this. We install a minimum of 8 inches of 21AA or similar crushed limestone aggregate. This material is installed in lifts (layers) and compacted with high-force centrifugal compactors (often rated at 5,000+ lbs of force). This creates a rigid, non-flexible beam that distributes the load of hot tubs, outdoor kitchens, or heavy foot traffic across a wide area, rather than letting point-loads puncture the subgrade.


3. The 1-Inch Chip Stone Bedding

Instead of using concrete sand, which can wash out or hold moisture against the pavers, we utilize a 1-inch layer of chip stone (ASTM No. 8). This angular stone locks the pavers in place while allowing water to flow freely through the bedding layer, preventing the "floating paver" effect during heavy rains.


Myth-Buster: "Won't the water under the patio cause problems?"

Homeowners often fear water getting under the pavers. The reality: Water will get under the pavers. The goal isn't to stop it, but to manage it. By using a permeable chip stone bedding and a compacted aggregate base, we allow water to drain vertically away from the surface, rather than pooling on top and turning into a skating rink in winter.


Comparison: The Professional Dig vs. The "Weekend Warrior"

Many DIY tutorials or budget bids omit the geotextile fabric and skimp on the base depth to save on disposal fees and material costs. In our climate, this is a fatal error.

Feature

The Salzman Standard (11-13" Dig)

The "Budget Bid" / DIY (4-6" Dig)

Excavation Depth

11–13 Inches

4–6 Inches

Base Thickness

8 Inches (Compacted)

2–4 Inches

Soil Separation

Heavy Geotextile Fabric (Standard)

None (Stone on Dirt)

Drainage

Directed away from foundation

Often pools in base

Failure Mode

Rare; Structural Warranty

Frost Heave & Rutting within 3 years

Best Use Case

Permanent Outdoor Living / Hot Tubs

Temporary Dog Runs / Garden Paths

Cost Strategy

Higher upfront, lower lifecycle cost

Low upfront, 100% replacement cost


STOP GUESSING TONNAGE.

Do not estimate your base requirements. Use our calculator to determine exactly how much aggregate is required for an 8-inch depth.

Freshly installed dark brown mulch

Our free mulch calculator.




Site Realities: Managing the "Clay Bowl"

We need to address a specific nuance of Michiana geology: The "Clay Bowl" Effect.

When we dig that 13-inch cavity into heavy clay, we have essentially built a swimming pool. If we fill it with stone but don't account for where the water goes, the patio will act as a reservoir. This is why we integrate your downspouts into the design.


Unilock Beacon Hill Alpine Grey paver patio installed in Berrien County MI

If a downspout is dumping 500 gallons of roof runoff right next to the patio during a storm, no amount of compaction will save you. We trench and pipe those downspouts away from the hardscape. We also laser-grade the patio surface to slope away from the home—usually at a 1% to 2% pitch—ensuring stability. We design for the heaviest load, whether that's a future hot tub or simply the weight of Michigan snow.


When is 6 Inches Enough?

Is an 11-inch excavation always necessary? If you are laying a simple stepping-stone path through a garden where slight movement adds "charm," or if you are overlaying an existing, structurally sound concrete pad (assuming elevation allows), deep excavation may be overkill. But for a contiguous patio intended for furniture and entertaining, the risk of frost heave is too high to cut corners.


The Next Step

You cannot see the quality of a foundation once the pavers are laid. The only time to verify the engineering is before the first stone goes down.


Schedule a Design Consultation. Let’s look at your soil conditions, your drainage patterns, and design a hardscape that stays exactly where we put it.